- What a liquidated damages clause is
- The enforceability question
- What makes a clause look like a punishment
- The ACL angle: standard form contracts
- Getting the amount right
- Where founders see these clauses
- The mechanics to read carefully
- Alternative structures worth knowing about
- Negotiating these clauses
What is a liquidated damages clause?
It is a clause that locks in the compensation amount upfront. Instead of fighting about what a breach actually cost you after the fact, both parties agree a number at signing. If the specified breach happens, that number applies automatically.
The amount can be a flat sum, a daily rate, a percentage of contract value, or some other formula. What matters is that it is fixed before anything goes wrong.
ExampleA software vendor agrees to deliver a platform by 1 October. The contract includes a liquidated damages clause: $2,500 per day for each day of delay past that date, up to a cap of $50,000. Delivery slips to 15 October. The vendor owes $35,000, regardless of what the customer actually lost during those two weeks.
The alternative, where no figure is agreed upfront, is that the innocent party has to prove their actual loss in court or arbitration. That is slower, more expensive, and uncertain. A well-drafted liquidated damages clause avoids all of that. The party enforcing it does not need to prove what they lost. They just need to show the breach happened.
That also means the defaulting party cannot argue the loss was unforeseeable or that the other side failed to minimise it. The agreed figure is the figure.
The enforceability question
Here is the catch. Australian courts will not enforce a liquidated damages clause if it looks more like a punishment than a compensation mechanism. A clause designed to punish rather than compensate is called a penalty, and penalties are unenforceable.
The test courts apply is whether the amount was a genuine attempt, at the time the contract was signed, to estimate the loss the innocent party would actually suffer. It does not have to be precise. It just has to be real.
Australian courts have also confirmed that this analysis is not limited to situations involving a breach of contract. Even where a payment obligation is triggered by an event that is not technically a breach, courts can still assess whether the amount is proportionate to the innocent party's legitimate commercial interests. If it is not, it may not be enforced.
What makes a clause look like a punishment?
Courts look at a range of factors. The main ones to understand as a founder are these.
The amount is wildly disproportionate to the actual harm
If the stipulated sum is far beyond the worst-case loss that could plausibly result from the breach, it is more likely to be struck down. The comparison is not to average expected loss but to the maximum conceivable loss at the time of contracting.
The clause is designed to coerce, not compensate
If the purpose of the clause is clearly to make breach so financially painful that a party simply cannot afford to default, regardless of the actual harm caused, courts treat that as a warning sign. The clause should be designed to put the innocent party in the position they would have been in, not to terrify the other side into performance.
The same amount applies regardless of the breach
A flat sum that applies identically to a minor slip and a catastrophic failure tends to suggest the number was not genuinely estimated against any particular harm. Graduated amounts, or amounts tied to specific and measurable breaches, are easier to defend.
Watch outIncluding wording that says the parties acknowledge the amount is a genuine estimate does not guarantee enforceability. If the figure is clearly excessive, an acknowledgment will not save it. Courts look at substance.
The ACL angle: an extra layer for standard form contracts
If you use standard form contracts with customers or small business counterparties, there is an additional risk layer that sits alongside the penalty analysis.
Under the Australian Consumer Law, a term in a standard form consumer or small business contract can be challenged as unfair if it creates a significant imbalance in the parties' rights, is not reasonably necessary to protect the interests of the party relying on it, and would cause detriment if applied. A liquidated damages clause that fails this test is void.
Since November 2023, the stakes increased. It is not just that an unfair term will not be enforced. Including or relying on an unfair term in a small business contract is now prohibited, and courts can order significant financial penalties for doing so.
Important for startups using standard termsIf you have a liquidated damages clause in your standard terms that you use broadly, proportionality is a compliance question, not just an enforceability one. Getting this wrong can result in financial penalties, not just a clause being set aside.
Getting the amount right: not just a ceiling problem
Most founders worry about setting the amount too high and having it struck down. But setting it too low creates its own problems.
A low amount combined with an exclusive remedy provision acts as a liability cap
If the clause says the liquidated damages are the innocent party's only remedy, and the amount is low, you have effectively capped your recovery. If something goes seriously wrong, that cap may leave you significantly under-compensated. If you are the party relying on the clause, make sure the amount actually reflects what you stand to lose.
A nominal amount can backfire
Where parties insert a token figure, such as one dollar, courts have found that this signals an intention not to create a real damages remedy at all. The result is that the innocent party retains the right to claim their actual loss through the courts instead. If you genuinely want to cap recovery at a small amount and exclude that claim, the contract needs to be explicit about it.
Practical noteFixing the amount is a commercial decision. A useful starting point is: what would it actually cost us if this specific obligation is not met? Keep a record of how you arrived at the figure. If the clause is ever challenged, that contemporaneous reasoning matters.
Where founders see these clauses
| Context | Typical trigger | Who it protects |
|---|---|---|
| SaaS and technology delivery | Late delivery, SLA breach, implementation delay | Customer |
| Supplier and manufacturing | Late or defective delivery of inputs | Buyer |
| Construction and fitout | Delay beyond practical completion date | Principal or tenant |
| Distribution agreements | Failure to meet minimum purchase commitments | Supplier |
| Key person and restraint arrangements | Breach of post-termination obligations | Employer or business |
| Outsourcing agreements | Service level failures, transition delays | Customer |
The mechanics to read carefully
A liquidated damages clause is more than a dollar figure. How the surrounding provisions are drafted determines how the clause actually works in practice.
The trigger event
What exactly activates the clause? Vague triggers, like "any breach" or "failure to perform," invite disputes about whether the clause has been activated. A tightly defined trigger, tied to a specific and measurable obligation, is cleaner to enforce and harder to contest.
When liability starts and when it stops
Where the clause runs at a daily rate, you need to know when it starts accruing and what stops it. Accrual typically begins at the trigger event. The obligation usually ends when the defaulting party remedies the breach, or when the innocent party terminates the agreement. Without a clear end point, a daily rate can run open-ended.
The aggregate cap
A daily rate without a cap creates unlimited exposure. Caps are usually expressed as a percentage of total contract value. If you are accepting a daily rate, always push for a cap.
Exclusive remedy or not?
Where the clause is expressed to be the only remedy for the relevant breach, the innocent party cannot also claim their actual loss on top. Check whether the exclusive remedy provision is limited to the specific breach the clause covers, or whether it sweeps more broadly across the agreement.
Payment and set-off
The clause should specify whether the amount is payable on demand, or whether the innocent party can deduct it from amounts they would otherwise owe to the defaulting party. The right to deduct is generally available at law, but spelling it out avoids arguments later.
A fallback if the clause does not hold up
If there is any doubt about whether the stipulated amount will be enforceable, a well-drafted agreement includes a fallback that preserves the right to claim actual loss if the liquidated damages clause is found void. That fallback can include its own cap, set at the same level as the liquidated damages figure, giving the other side certainty about their maximum exposure regardless of which route is taken.
Carve-outs for things outside your control
If you are the party accepting potential liability, push for carve-outs where delay or default results from the other party's actions, third-party dependencies, or events beyond your control. Without these, you can be liable for delay you had no ability to prevent.
Alternative structures worth knowing about
There are a few ways to achieve a similar commercial outcome without the same enforceability risk.
One approach is to reward performance rather than penalise default. A bonus for early delivery achieves a similar incentive effect to a damages clause for late delivery, but without the same legal constraints. Another is to structure payment terms so that a debt is already due, but the creditor agrees to accept a lower amount or deferred payment if certain conditions are met. If those conditions are not satisfied, the original amount becomes payable immediately. Instalment agreements sometimes work this way, with a full acceleration clause on default.
Worth notingThese structures are not risk-free. Courts can look through any arrangement and assess whether it is operating as a punishment in substance, regardless of how it is framed. But they are worth considering where the standard clause structure raises enforceability concerns.
Negotiating these clauses
If you are the one accepting potential liability
- Is the trigger event within your control? If not, push for carve-outs.
- Is there a periodic rate without a cap? Push for one.
- Is the clause expressed as the other party's exclusive remedy, or can they claim actual loss on top?
- Is there a cure period before liability starts to accrue?
- Does the rate bear any relationship to the other party's actual anticipated loss? If not, you have grounds to negotiate it down.
If you are including the clause in your own contracts
- Keep a record of how you arrived at the figure at the time of drafting.
- Target the clause at specific breaches, not any default under the agreement.
- Avoid rates that are clearly out of proportion to your actual anticipated loss.
- If you use standard form contracts with small business counterparties, run the ACL unfair terms analysis as well.
- Include a fallback general damages provision in case the clause is found unenforceable.
Liquidated damages clauses are a genuinely useful commercial tool when they are put together properly. They give both sides certainty, reduce the cost of disputes, and make risk allocation something you can actually plan around.
The problem is not the clause itself. It is accepting one without understanding what you are agreeing to, or including one that will not hold up when you need it. Both of those outcomes are avoidable if you get the structure right at the drafting stage.
Need help reviewing or drafting a liquidated damages clause?
Plumlaw works with founders and scale-ups on commercial contracts at fixed fees. No hourly billing, no surprises.
Get in touch